Uganda Security Printing Company
2 recorded entries in 1 country: Uganda.
2register entries
1country
2018 to 2023recorded date range
1adverse official findings
0favourable official findings
Entries by status
Funding recorded across these entries: Concession or PPP: 1. Not published: 1. These are entry counts, not contract-value totals.
- Under review 2
| Country | Programme | Vendor | Funding | Status | Signed |
|---|---|---|---|---|---|
| Uganda | NIRA identity-data disaster-recovery contract | Uganda Security Printing Company | Not published | Under review | 3 May 2022 |
| Uganda | Security-document production joint venture | Uganda Security Printing Company | Concession or PPP | Under review | 4 October 2018, according to… |
Oversight record in date order
- Uganda: 23 December 2022: Auditor General found full payment before delivery, missed deadlines, absent performance security and insufficient progress reports. Management cited a vendor delivery commitment and USPC's government-ownership explanation for not providing security. The auditor maintained the recommendations. The unmodified financial-statement opinion is not contract clearance 1.
- Uganda: 30 March 2023: COSASE questioned selection and due diligence. Nathan Itungo suggested the supplier was handpicked. Finance official Christopher Mugisha said an evaluation committee applied criteria under Attorney General guidance and defended legal and financial due diligence. The committee requested procurement documents. The report records a hearing, not a final finding 4.